Priya and Dave put every inspection in the client's plan on the parts list, and every hold point into the programme, like a concrete delivery. Nothing pours until the record exists.
The inspection nobody planned
Before you start
In the story
The steel was probably fine. Nobody could prove it.
The right way
The Clerk of Works inspects the steel and signs it off on the site app, against the right drawing, with photos.
Six trucks. Pour. On Monday the Clerk of Works nods. Very nearly smiles.
Every inspection is a piece of information you owe someone. In week one, ask: which inspections, who does them, how much notice, and where does the record go? If it isn't planned, it won't happen. If it isn't written down, it didn't.
Story 2: The briefing on C01
The method statement went to C02. The copy on the cabin wall is still C01.
The right way, explained
Some roads in town have a toll booth you can't drive round. A hold point is a toll booth: it goes on the map before anyone sets off, not after they've driven through it.
If you're the site manager
Book inspections the way you book concrete: with a date, a name and notice. Nothing pours until the record exists. "It looked fine" is not a record.
In the town See it in the town: the steel was probably fine. How much does "probably" cost?
Priya's view: the parts list isn't only drawings. Every inspection record the client needs is on it too, with a name and a date.
Inspection records are information too!
Each one is owed to someone, planned in week one, and on the parts list like any drawing.
Sam's Heads Up It might not be called an inspection plan
InfoTown good practice: Plan what you owe, with an owner and a date.
On your job: Your job might call it an inspection and test plan, a quality plan or a hold-point schedule. Whatever it's called, it sits next to the delivery plan, not in a drawer.
For the audit What the auditor will ask
- Show me the inspection plan, and where the hold points sit in the programme.
- Show me the record for this pour.
For the audit What good evidence looks like
- An inspection plan with hold points, owners and notice periods.
- A signed record for each hold point, against the right drawing revision, dated before the pour.
ISO 19650 Planning what's delivered
ISO 19650 expects the information a team has to deliver to be planned up front, each piece with an owner and a date. That inspection records belong on that plan is InfoTown's advice; how you run inspections is your quality system, not ISO 19650.
Based on the ISO 19650 series: the ideas come from the standard; the plain-English wording, examples and advice are InfoTown's. ISO 19650 is © ISO and BSI. You'll hear the same language across the industry. Read more for free in the Information Management Initiative (IMI) Framework guidance from BSI and nima. For the full requirements, use the standard itself.