Sam gets one master agreed in writing: the client's CDE.
Which one's the real one?
Before you start
In the story
Three systems, two "latest" drawings, and a Clerk of Works who is not smiling.
The right way
Every other system gets a clear job: work in progress, and nothing anyone builds from. It's tested with a dummy drawing; joiners get access on day one, and leavers lose it on their last.
Stevie uploads once. Alex, site and the Clerk of Works all see the same survey.
For every system on your job, can you say whether it's the master, a workspace, or neither? Anything that's "a bit of both" is where two latest drawings come from.
Story 2: The plan grows up
The bid's information plan won the job. Then it went in a folder called TENDER.
The right way, explained
A town can have many buildings, but only one Records Office everyone agrees to trust. Two post offices both claiming to be the real one is how parcels go missing.
If you're the project manager
Make it your rule, not Sam's: one master, and nobody on your team builds from anything else. Back Sam when someone says "but I've always used the drive".
In the town See it in the town: three places claim to be the real one. Which one counts?
Sam's view: one Site Office for the job, joined to every town by its own line. That's the one that counts.
Now mobilise it: build and connect the site
In the middle sits the Site Office: the project's CDE, joined to your own Records Office by the home line. Lines run out to every town: the design line to the designers, the client line to the client, the home line back to your own Records Office, the feeder line to the site apps and footpaths to the cabins. The workflows running along all these lines are how one system passes work to another. Signposts tell everyone where each kind of work goes, and the gate decides who gets in.
- Build the Site Office
- Connect the towns
- Plug in the site apps
- Put up the signposts
- Set up the gate
- Test everything
The towns are there. The project site is an empty plot. Your job: mobilise it.
This is the Common Data Environment (CDE)!
The one place everyone shares from and builds from.
For the audit What the auditor will ask
- Which system is the single source of truth, and where is that agreed?
- Pick a joiner and a leaver: when did their access start and stop?
For the audit What good evidence looks like
- The master CDE named in the confirmed plan.
- A test record from before go-live.
- An access log showing joiners and leavers.
ISO 19650 The CDE, set up and tested
ISO 19650 expects one common data environment for the project, set up and tested before information starts moving, with the rules for what goes where agreed up front.
| Expect | In plain words |
|---|---|
| One agreed CDE | The master. Everything shared or published lives there |
| Other systems with a clear job | Work in progress, never the place anyone builds from |
| Tested before go-live | Upload, share and find a dummy file before the real ones arrive |
| Access managed | Joiners added, leavers removed, on the day |
Based on the ISO 19650 series: the ideas come from the standard; the plain-English wording, examples and advice are InfoTown's. ISO 19650 is © ISO and BSI. You'll hear the same language across the industry. Read more for free in the Information Management Initiative (IMI) Framework guidance from BSI and nima. For the full requirements, use the standard itself.