Bev's journey · Procurement · Story 1

Three quotes, three different things

Three firms quote for The Glasshouse's electrics. Each has priced different information, because nobody said what was needed.

The wrong way

The enquiry

Bev sends the electrical package to three firms: drawings, a specification and a deadline. Three quotes, as always.

The enquiry

Nothing in it says what information comes back: models, asset data, test records, or in what format.

The quotes

£410,000, £385,000 and £340,000. Bev's spreadsheet likes the third one.

Small print

The cheapest firm priced drawings and a PDF handover. The other two priced asset data in the client's format.

BuildBuild: Month eight…
Month eight

Contract signed with the cheapest. Sam asks for the asset data. "Not in our price."

Month eight

Bev: Three quotes. For three different jobs.

The variation costs £75,000. The cheapest quote is now the dearest.

The cheapest quote left out the information, so it wasn't the cheapest.

Find out what Bev should have done

Bev's Lesson 1 · Three quotes, three different things, then the same story done the right way.