Kofi's journey · Commercial · Story 1

Who pays when the infor­mation changes?

The client asks for extra asset data by email. The team just does it.

The wrong way

DesignDesign: Month two…
Month two

The client's asset manager emails Sam: "Could you add the valve serial numbers and maintenance intervals? Should be quick."

Month two

Nobody checks whether it's in what we agreed to deliver. It isn't. The team says yes, because it's nice to be helpful.

Evenings

Rex spends his evenings typing serial numbers off nameplates.

Months three to five

More emails arrive: warranty dates, spare parts, a photo of every valve. Each one "should be quick".

BuildBuild: Month six…
Month six

Kofi reads the cost report: £60,000 of information work nobody priced.

Month six

Kofi asks the client to pay for the change. Client: "You never said it was extra. You just did it." Kofi looks at his calculator. The calculator agrees with the client.

Four months of extra work, no change agreed, and nobody paid.

Find out what Kofi should have done

Kofi's Lesson 1 · Who pays when the information changes?, then the same story done the right way.