Lessons learned
It turns into who blames whom. Nothing gets written down. Priya twitches.
The job's handed over. Everyone moves on. Nobody closes the door behind them.
The wrong way
It turns into who blames whom. Nothing gets written down. Priya twitches.
Which drive? "The drive."
Nobody closes the project. It's one of 300 "live" projects on the CDE. Leavers from three jobs ago can still log in.
Finance spots the licence bill for 300 projects and asks IT to tidy up.
IT deletes everything older than a year. Including The Glasshouse.
The client raises a defect on the inlet chamber and asks for the inspection records. We've got an email saying they're "on the drive".
We kept it safe until someone tidied up. The defect claim arrived after.
Find out what Sam should have doneSam's Lesson 10 · It's all on the drive, then the same story done the right way.