Stevie's team finishes a fresh ground survey of the whole site. He saves it to his laptop, in a folder called SURVEY_NEW.
Stevie's journey · Engineering · Story 1
The survey nobody could find
The new survey is done. The designers are using one from five years ago.
The wrong way
Get readyGet ready: Month one…
Month one
Design office
Alex asks for a survey. Someone finds one in the client's old archive. It's five years old. Nobody checks the date.
Since then
The client has built a car park and raised the access road. The old survey has never heard of either.
Design
Alex designs the levels from it: the inlet, the access ramp, the drainage falls. Beautifully.
DesignDesign: Month four…
On site
The new ramp meets the road 400mm below it.
Rex: Is that meant to be a step?
Redesign
Levels, drainage and kerbs, all redesigned. Alex: "We used the survey we had." Stevie looks at his laptop. "Aye. That one's on me."
The right survey existed. It was on Stevie's laptop.
Find out what Stevie should have doneStevie's Lesson 1 · The survey nobody could find, then the same story done the right way.