HandoverHandover: The last month…
The last month
Handover is due and somebody asks for the as-built drawings.
Forty design drawings, one afternoon, one rubber stamp that says AS BUILT.
The wrong way
Handover is due and somebody asks for the as-built drawings.
The design drawings get AS BUILT stamped on them. Forty drawings, one afternoon, one stamp.
Rex: "Shouldn't someone check them first?" Everyone is very busy.
The overflow manhole moved 1.2m to dodge a cable nobody knew about. It was agreed with a photo and a thumbs-up.
The client accepts the pack. Everyone goes home.
The operator's crew digs where the drawing says the manhole is. They find a fence post. The manhole is 1.2m away, under a parked van.
The drawings said "as built". They meant "as drawn".
Find out what Stevie should have doneStevie's Lesson 7 · Drawn versus built, then the same story done the right way.