Tom's journey · Pre-Construction · Story 1

Should we even bid?

The go or no-go meeting looks at price, programme and risk. Nobody mentions the information requirements.

The wrong way

Friday

The go or no-go meeting for The Glasshouse: price, programme, risk, margin. Coffee.

Friday

Nobody has read the information requirements. Tom: "Standard stuff, probably."

Go

Four weeks of bid work, three people, one tired Tom.

Win the workWin the work: Week three…
Week three

Sam finally reads them: the client's own CDE, a digital twin, and data in a format we've never used.

Week three

None of it is priced, and there's no time left to price it properly.

Week four

Tom: We could have known on Friday.

They bid anyway, with a guess.

Three weeks into the bid, someone read the information requirements. They'd been there since Friday.

Find out what Tom should have done

Tom's Lesson 1 · Should we even bid?, then the same story done the right way.