Kofi lines the payment plan up with the delivery milestones. Before each one he checks with Sam: what's due, has it been checked, will it pass?
Paid on acceptance
Before you start
In the story
A wrong file name held up £400,000.
The right way
Sam checks the package against the client's requirements before it goes. It's accepted first time.
Kofi's forecast moves when an acceptance date moves, not when the money fails to arrive.
When does the money actually arrive? If payment hangs on acceptance, the delivery plan is a cash-flow forecast. Do you know what's due, and whether it'll pass?
Story 6: The cost nobody booked
Bad information is costing the job a fortune. Nobody can say how much, because it's booked to everything else.
The right way, explained
The town pays for parcels when they're signed for, not when they're sent. Send the wrong colour wardrobe and nobody pays until the right one arrives.
If you're the project manager
Put the information milestones in your programme next to the payment ones. A deliverable rejected the week before payment is a cash problem, not just a quality one.
In the town See it in the town: a wrong file name held up £400,000. What's the link?
Kofi's view: signed out by us, signed for by them. The money follows the second signature.
Shared
- On the label
- IM calls it
- Watch out for
These are Information Delivery Milestones!
The dates information is due and accepted, which on many contracts is also when you get paid.
Sam's Heads Up Not every contract pays this way
InfoTown good practice: Information is delivered and accepted at agreed milestones.
On your job: Plenty of contracts pay on progress, not acceptance. Read yours. If payment does hang on acceptance, my delivery plan is Kofi's cash flow.
For the audit What the auditor will ask
- Show me the delivery milestones, and what was accepted at each.
- What happens when a deliverable is rejected?
For the audit What good evidence looks like
- Delivery milestones lined up with the payment plan.
- Acceptance and rejection records, with reasons.
ISO 19650 Delivery milestones
ISO 19650 expects information to be delivered at agreed milestones and accepted by the client. Whether payment depends on acceptance is set by your contract.
Based on the ISO 19650 series: the ideas come from the standard; the plain-English wording, examples and advice are InfoTown's. ISO 19650 is © ISO and BSI. You'll hear the same language across the industry. Read more for free in the Information Management Initiative (IMI) Framework guidance from BSI and nima. For the full requirements, use the standard itself.