The contract
It pays a chunk at each milestone, once the client accepts what's due.
Payment is tied to accepted deliverables. Ours keep coming back rejected, so the cash is held.
The wrong way
It pays a chunk at each milestone, once the client accepts what's due.
Kofi's cash-flow forecast assumes the money arrives on the milestone date. Nobody mentioned acceptance.
The design package goes to the client. Rejected: wrong file names, two models missing.
Fixed and sent again. Rejected again: a different reviewer with different comments.
It's accepted. The money arrives six weeks late.
Finance asks Kofi why the job is £400,000 overdrawn. Kofi: "Because a file name was wrong." Finance doesn't laugh.
A wrong file name held up £400,000.
Find out what Kofi should have doneKofi's Lesson 5 · Paid on acceptance, then the same story done the right way.