The electrical firm turns up. Nobody has set up their CDE accounts. Licences weren't in anybody's price.
Bev's journey · Procurement · Story 2
Signing up the subbie
The new electrical firm starts on Monday. Nobody ordered their logins, so everything comes by email.
The wrong way
Get readyGet ready: Monday…
Monday
Monday
"Just email it for now," says someone helpful.
Week two
Rex's inbox fills with their drawings: ELEC_FINAL, ELEC_FINAL2, ELEC_FINAL_USE_THIS.
Week three
Rex forwards them to Sam, Dave and Alex. Mostly.
DesignDesign: Week six…
Week six
The firm still has no logins, and their engineer has never had the training.
Week six
Bev: Nobody asked me for logins.
Sam finds 140 of their drawings that never reached the CDE. Bev checks the order: licences and training, not mentioned.
Six weeks of drawings in Rex's inbox, because nobody ordered the logins.
Find out what Bev should have doneBev's Lesson 2 · Signing up the subbie, then the same story done the right way.