HandoverHandover: Handover month…
Handover month
The supplier sends the escalator documents: 40 PDFs, a catalogue and a brochure with a beach on it.
The escalators arrive with 40 PDFs. The serial numbers the maintenance team needs aren't in any of them.
The wrong way
The supplier sends the escalator documents: 40 PDFs, a catalogue and a brochure with a beach on it.
They need serial numbers, spares lists and maintenance intervals, in their asset system's format.
None of it is in them. Some of it is in a catalogue covering 200 models.
It never said what product data comes back, or in what format.
"We sent what we always send." They're right.
Sam's team types data off nameplates, and the client holds the handover payment until it's done.
Forty PDFs, and not one had what the maintenance team needed.