Bev's journey · Procurement · Lesson 3

Ordered off the old spec

Before you start

In the story

The right escalators were on C02. The order was for C01.

Back to the story

The right way

Every order

It names the specification and drawings it's placed against, with their revisions, and Bev checks they're still current on the CDE before it goes.

When it changes

The designer's revision to a specification already on order comes to Bev, and on to the supplier.

Delivery day

The right escalators arrive. Rex signs for them, Stevie checks the nameplate, and nobody says "which spec?"

"What the spec said"No revision on the order, the wrong escalators, and sixteen more weeks.
Which spec, written downThe revision on the order, checked before it went, and the right escalators.
Think like Bev

An order is a promise to make exactly what's written. Which revision is it written against, and is that still the current one? Write it on the order.

Continue Bev's journey

Story 4: The product data nobody asked for

The escalators arrive with 40 PDFs. The serial numbers the maintenance team needs aren't in any of them.

The right way, explained

The right way, explained

The town's order desk keeps a copy of exactly what was ordered, revision and all. When the plans change, the desk tells the factory, not just the architect.

If you're the subcontractor

If you're the subcontractor

Check the revision on the order against the latest one you've been sent. If they don't match, ask before you make anything.

In the town See it in the town: the right escalators were on C02. Why did C01 turn up?

Bev's view: the label says which revision is in the box. The order should say the same.

Goods In at the Site Office A long sorting hall. Parcels with labels travel along a conveyor belt and are routed to the Design System, the Site Office, the Client Town and the Archive. One parcel has no label. The sorter's scanner shows a question mark and the parcel drops into the in-tray. SITE OFFICE · GOODS IN PARCEL LABEL P1234-ABC-XX-A2-D-C-0042 Drainage layout, Area 2 Rev P03 · S2 Suitable for information ? DESIGN SYSTEMTHE SITECLIENT TOWNRECORDS OFFICE THE IN-TRAY ?
Labelled. Sorted and sent to the right place.
No label. Stuck in the in-tray.
Read the label

Every part of the label answers a question

It looks like a code, but each part answers a plain question. Pick any part to see what it tells you.

Parcel labelDrawing 042
- - - - - -
Title Revision Status

Is it the latest?

P03 is the third preliminary revision. While it's being worked on it also carries a version, like P03.02. When it becomes part of the contract it starts again as C01.

On the label
P03
IM calls it
Revision
Why it matters
Without it, four files called FINAL all look equally right.

An order carries information too!

A purchase order carries information, the specification and drawings with their revisions, and it has to be current.

Sam's Heads Up Long-lead items move after you order them

InfoTown good practice: Orders are placed against the current revision.

On your job: On long-lead items the design can still change after the order. Agree with the designer which documents are frozen when you order, and who tells you if they move.

For the audit What the auditor will ask
  • Which revision of the specification was this order placed against?
  • How do design changes reach orders that are already placed?
For the audit What good evidence looks like
  • Orders that name their documents and revisions.
  • A link between design changes and open orders.
From the standard
ISO 19650 Revisions on everything

ISO 19650 expects information to carry its revision and status, and people to work from the current one. Using an order as the example is InfoTown's; how you place orders is your procurement process.

Based on the ISO 19650 series: the ideas come from the standard; the plain-English wording, examples and advice are InfoTown's. ISO 19650 is © ISO and BSI. You'll hear the same language across the industry. Read more for free in the Information Management Initiative (IMI) Framework guidance from BSI and nima. For the full requirements, use the standard itself.