Kofi's journey · Commercial · Story 2

Measured from the wrong drawing

Kofi values the month's work from Rex's quantities. Rex measured from C02. The basement is now on C03.

The wrong way

DesignDesign: Month three…
Valuation week

Month three. Kofi needs the concrete and excavation quantities by Thursday.

Tuesday

Rex takes them off the basement drawing in his downloads folder: C02.

A fortnight earlier

C03 was published. The basement went 2m deeper.

Thursday

Kofi's valuation goes in. The client's quantity surveyor measures from C03.

The week after

The two numbers are £40,000 apart. Each side is sure the other can't count.

Two weeks later

A week of arguing, a week of re-measuring, and the payment is late. Kofi asks which drawing Rex measured from. Rex: "The one I had."

£40,000 apart, and both sides measured right. From different drawings.

Find out what Kofi should have done

Kofi's Lesson 2 · Measured from the wrong drawing, then the same story done the right way.