Rex measures from the current published drawings on the CDE, and every measure says which drawing and revision it came from: "Basement, C03".
Measured from the wrong drawing
Before you start
In the story
£40,000 apart, and both sides measured right. From different drawings.
The right way
Kofi's valuation lists the drawings it's based on, so the client's quantity surveyor measures from the same ones.
The numbers agree to within rounding. Kofi files it without a fight, which worries everyone.
A number is only as good as the drawing it came from. Which drawing, which revision, and is that still the current one? If you can't write it next to the number, don't send the number.
Story 3: The notice that never arrived
The ground is worse than the survey said. The contract says how, and how fast, to tell the client. Nobody reads that part.
The right way, explained
You can't count the houses on a street from last year's map. Both sides need the same map before they argue about the count.
If you're the project manager
When the design changes, tell the commercial team the same day. A deeper basement is a cost question before it's a site question.
In the town See it in the town: £40,000 apart, and both sides measured right. How?
Kofi's view: the published shelf. Everyone counts from the same copy, or they argue about the count.
Shared
- On the label
- IM calls it
- Watch out for
This is working from the published version!
Measure, price and build from what's been published, and say which revision you used.
Sam's Heads Up Downloads folders are where revisions go to hide
InfoTown good practice: Work from the current published version on the CDE.
On your job: People will download drawings to measure from. Fine, as long as the revision goes on the measure and someone checks it's still current before the valuation goes in.
For the audit What the auditor will ask
- Which drawings was this valuation based on?
- How did you know they were current?
For the audit What good evidence looks like
- Measures that name their drawings and revisions.
- Valuations that list the drawings they used.
ISO 19650 Working from the published version
ISO 19650 expects people to work from information shared or published in the CDE, with its revision and status shown. Using it to value work is InfoTown's example, not the standard's.
Based on the ISO 19650 series: the ideas come from the standard; the plain-English wording, examples and advice are InfoTown's. ISO 19650 is © ISO and BSI. You'll hear the same language across the industry. Read more for free in the Information Management Initiative (IMI) Framework guidance from BSI and nima. For the full requirements, use the standard itself.