Sam's journey · On the job (delivery) · Story 3

Who makes what, and when

The delivery plan lists two hundred drawings. It was last opened at tender.

The wrong way

Get readyGet ready: Month one…
Month one

It hasn't been opened since tender.

Month one

Alex's firm makes the drawings they think are needed.

DesignDesign: Month two…
Month two

Rex gets a beautiful drawing of a fence nobody asked for, and nothing for the inlet chamber due next week.

Month two

Site asks for the inlet chamber drawing. It isn't on anyone's list.

Month two

The programme slips two weeks while it's drawn in a hurry.

Month two

Sam: Who's making the inlet chamber drawing?

Three firms point at each other.

Two hundred drawings planned, one fence nobody asked for, and the one that mattered on nobody's list.

Find out what Sam should have done

Sam's Lesson 3 · Who makes what, and when, then the same story done the right way.