Before the contract is signed, each team writes its own plan: what it'll make, when, and who's doing it.
Who makes what, and when
Before you start
In the story
Two hundred drawings planned, one fence nobody asked for, and the one that mattered on nobody's list.
The right way
Sam rolls them into one master plan, lined up with the build programme, with who produces each piece, and when, written down team by team. Both go into the appointment.
Issued at C01 after award, the plan stays live. When the programme moves, the plan moves. The inlet chamber drawing arrives a week early.
Pick the next three things site needs. Are they on the master plan, with a firm, a person and a date? If not, that's this week's job.
Story 4: Ready before day one
The bid had a mobilisation plan. Now somebody has to actually do it.
The right way, explained
The parts list for the town: what's being made, by whom, and when it has to arrive. A parts list written at tender and never opened is a wish list, not a plan.
If you're the project manager
The master delivery plan should sit next to your programme. If one moves and the other doesn't, ask why.
In the town See it in the town: every team's page of the parts list. What happens when you join them up?
Sam's view: every team's page of the parts list, joined up into one, and lined up with the programme.
These are the Task and Master Information Delivery Plans!
Each team's page of the parts list, put together into one.
For the audit What the auditor will ask
- Show me the master delivery plan, and how it lines up with the programme.
- Show me who's responsible for one item, and how you know.
For the audit What good evidence looks like
- Each team's delivery plan.
- The master plan with dates.
- The responsibility matrix.
- Updates over time.
ISO 19650 Delivery plans and who does what
ISO 19650 expects each team to plan what information it will produce and when, and the lead firm to roll those into one master plan, alongside a detailed matrix of who is responsible for what. All of it is done before the appointment is made, so it forms part of the appointment.
| Expect | In plain words |
|---|---|
| Team delivery plans | Each team's list: what, when, who |
| The master delivery plan | All of them together, lined up with the programme |
| The responsibility matrix | Who produces each piece, and when (the procedures say who checks and approves) |
| Kept live | Updated whenever the programme or the scope moves |
Based on the ISO 19650 series: the ideas come from the standard; the plain-English wording, examples and advice are InfoTown's. ISO 19650 is © ISO and BSI. You'll hear the same language across the industry. Read more for free in the Information Management Initiative (IMI) Framework guidance from BSI and nima. For the full requirements, use the standard itself.