BuildBuild: Week six…
Week six
Bev places the escalator order, quoting the specification attached to the enquiry: C01.
Bev orders the escalators against the specification in the enquiry. It changed a fortnight earlier.
The wrong way
Bev places the escalator order, quoting the specification attached to the enquiry: C01.
The designer reissued it as C02. Heavier escalators.
It doesn't say which revision it was placed against, so nobody spots it.
The escalators arrive. Rex signs for them. They look like escalators.
Stevie checks the nameplate against the schedule. Wrong escalators.
Sam: Which spec?
New order: sixteen more weeks, and a restocking charge for the old ones. Bev: "I ordered what the spec said."
The right escalators were on C02. The order was for C01.
Find out what Bev should have doneBev's Lesson 3 · Ordered off the old spec, then the same story done the right way.