Drawings from the client's designer come through the CDE, not by email, and the CDE records who shared what, which revision, and when everyone was told.
The claim you can't prove
Before you start
In the story
Three weeks late, and no way to prove it.
The right way
Kofi pulls the record: due on the 3rd, published on the 24th. Three weeks.
It goes in with the record attached. Kofi has his evidence in ten minutes, and the client doesn't argue the dates.
If this ends in an argument, could I prove when it happened? If the answer is "it's in an email somewhere", it isn't evidence yet.
Story 5: Paid on acceptance
Payment is tied to accepted deliverables. Ours keep coming back rejected, so the cash is held.
The right way, explained
The town's post office stamps every parcel in and out. When there's an argument about when something arrived, nobody searches their pockets; they ask the post office.
If you're the project manager
Insist that information from the client's side comes through the CDE too. An email straight to site is quick, and it's also the first thing a claim loses.
In the town See it in the town: three weeks late, and no proof. Where should the proof have been?
Kofi's view: the Site Office records everything in and out. That record is the evidence.
Now mobilise it: build and connect the site
In the middle sits the Site Office: the project's CDE, joined to your own Records Office by the home line. Lines run out to every town: the design line to the designers, the client line to the client, the home line back to your own Records Office, the feeder line to the site apps and footpaths to the cabins. The workflows running along all these lines are how one system passes work to another. Signposts tell everyone where each kind of work goes, and the gate decides who gets in.
- Build the Site Office
- Connect the towns
- Plug in the site apps
- Put up the signposts
- Set up the gate
- Test everything
The towns are there. The project site is an empty plot. Your job: mobilise it.
This is the record of every exchange!
The CDE's trail of who shared what, which revision, and when.
Sam's Heads Up The CDE can't remember what it never saw
InfoTown good practice: Everything shared goes through the CDE, so it's on the record.
On your job: Some things will still arrive by email. Put them in the CDE the same day, with the date they arrived, or the record has a hole exactly where you'll need it.
For the audit What the auditor will ask
- Show me when this drawing was received, and who was told.
- How do you deal with information that arrives outside the CDE?
For the audit What good evidence looks like
- A CDE record of each exchange, with dates and revisions.
- A rule for logging anything that arrives another way, and proof it's followed.
ISO 19650 The record of every exchange
ISO 19650 expects the CDE to keep a record of every exchange: what, which revision, who and when. Using that record in a claim is InfoTown's example; the claim itself is your contract's business.
Based on the ISO 19650 series: the ideas come from the standard; the plain-English wording, examples and advice are InfoTown's. ISO 19650 is © ISO and BSI. You'll hear the same language across the industry. Read more for free in the Information Management Initiative (IMI) Framework guidance from BSI and nima. For the full requirements, use the standard itself.