Stage 4 · Design it · Stop 6 of 7 · The right way

Authorised and accepted

The back alley's bill so far: 85 weeks · See the bill

← Back to the wrong way

The right way

DesignDesign: Week 13, Monday…
Two desks

042 goes to Aisha, the lead firm's design manager, at S4: complete, coordinated, does what was asked. She authorises it. Then the client's reviewer accepts it at S5.

Published

Tuesday, 2pm: 042 goes on the published shelf, labelled C01 and A5. Site is told, with a link. The pour moves to Wednesday.

Dave: A day late, from the right drawing. Fine.

DesignDesign: Three weeks later…
Spot on

The Clerk of Works checks the pipe level against the published 042. Spot on. He very nearly smiles.

The photoA pour on Monday, a pipe 150mm high, and no proof.
The published shelfA pour on Wednesday, the right level, and a Clerk who nearly smiled.

Now there is: Drawing 042 on the published shelf, through the authorise and accept checkpoints (authorised and accepted, the published state).

What's going on here

Site builds from what's published, and only from what's published. The lead firm authorises it and the client accepts it, so what's on the shelf is complete, checked and agreed. A photo of a drawing still being checked saves a day and costs a pipe.

New at this stop

Authorise and accept
Two checks before anything is published: the lead firm authorises it (complete, and does what was asked), then the client accepts it. S4 and S5 on the label mean it's at those desks.
A codes (A5, A6)
The label on published work: authorised and accepted. The number is the work stage: 5 for building, 6 for handing over.
In the town See it in the town: The drawing was ready. Was it allowed out yet?

Drawing 042 leaves Alex's own room for the shared table at S1, which is for building around, not building from. Before it reaches the published shelf it passes two desks: the lead firm authorises it at S4, then Client Town accepts it at S5. Only then does it get A5 and a C revision on its label, and site gets a link. The photo on the cone skipped both desks, so nothing on any label could vouch for it.

Fix it Building from something unpublished? Stop and check the label.
  1. Ask site which drawings they're building from today, and where from.
  2. Check each label: anything without A5 and a C revision goes back.
  3. Agree how fast the two desks turn round urgent drawings.

A note for the information manager: If site keeps asking for "just the drawing", the published shelf is too slow for them, and that is yours to fix, not theirs to work round.

Try it on your job

Next time someone asks you to "just send the drawing", check what its label says first.

From the standard
ISO 19650 From two desks to the shelf
ISO 19650 saysMeansIn the town
AuthorisationThe lead appointed party's check that information is complete, coordinated and does what was asked, before it goes to the clientAuthorise, the S4 desk
AcceptanceThe appointing party's review of the information it receives, deciding whether to take it as deliveredAccept, the S5 desk
Published stateInformation that has been authorised and accepted and can be used, for example for constructionThe published shelf, A5 on the label
StatusA code on each piece of information saying what it may be used forStatus codes on the label

Based on the ISO 19650 series: the ideas come from the standard; the plain-English wording, examples and advice are InfoTown's. ISO 19650 and its UK National Annex are © ISO and BSI. You'll hear the same language across the industry. Read more for free in the Information Management Initiative (IMI) Framework guidance from BSI and nima. For the full requirements, use the standard itself.