The night before

The back alley's bill so far: 79 weeks · See the bill

The information · Every firm's model, before the milestone

Every firm has checked its own part of me. Nobody's looked at all of me together yet. Do it before the milestone, not the night before.

The wrong way

DesignDesign: Milestone week…
Every firm checked

The design milestone is Friday. Every firm has checked its own models. Nobody has put them together.

Together, at last

Thursday, 9pm. Josh, the model coordinator, puts all the models together for the first time. The pipework runs through the plant room wall. A cable route goes up the stairs.

Fourteen hours

Forty clashes. Fourteen hours to go. It goes to the client anyway.

DesignDesign: Two weeks later…
The comments

The client's comments come back: forty of them.

The same forty

Josh holds them up against his Thursday-night list. It's the same forty, in a slightly different order.

Two weeks

Two weeks answering them. The pizza box is still on the desk.

Every piece checked. The whole thing looked at for the first time, the night before, and then again by the client.

+2 weeks on the back alley's bill: Laid out the night before: forty clashes sent to the client, and two weeks answering them.