Now I have to tell the truth about what was actually built, not what was drawn. A stamp can't do that. A tape measure can.

The wrong way

HandoverHandover: The last month…
Somebody asks

Handover is due, and somebody asks for the record of what's been built. Nobody has started it.

One afternoon

The design drawings get AS BUILT stamped on them. Forty drawings, one afternoon, one stamp.

A question

Rex, the new assistant engineer, has a question for Dave, the site manager.

Rex: Shouldn't somebody check them first?

Dave: They're as built. It says so.

In useIn use: Two years later…
The dig

The maintenance crew digs where the drawing says the manhole is. They find a fence post.

In use
Month seven

Back in month seven, the overflow manhole moved 1.2 metres to dodge a cable nobody knew was there. Agreed with a photo and a thumbs-up. It never reached a drawing.

In use
Under the van

Grace, the client's asset manager, finds the manhole 1.2 metres away, under a parked van.

Crew: The drawing says 'as built'.

Grace: It meant 'as drawn'.

Forty drawings, one stamp, one afternoon. The drawings said "as built". They meant "as drawn".

+2 weeks on the back alley's bill: Design drawings stamped AS BUILT: a manhole that isn't where the record says, and a crew digging in the wrong place.