The information · The client's order, and the firms the lead brings in

The client told the lead firm what it needs from me. Now every firm the lead brings in needs to hear it too, before they price, not after they've drawn.

The wrong way

Get readyGet ready: Week two…
The folder called CLIENT

The client's order goes into a folder called CLIENT. Designer Alex's firm is appointed with a one-page letter that says "BIM to client requirements".

House style

Alex draws in his firm's house style: their naming, their templates, their favourite shade of blue. It looks lovely.

By email

The subcontractors start work with no logins. Their drawings arrive by email, attached, zipped, and named DRAWINGS.

DesignDesign: Month three…
Nobody told us

None of it matches the client's order.

Alex: Nobody told us.

Sam (information manager): It's in the folder called CLIENT.

Four weeks of renaming

Every drawing has to be renamed, re-templated and re-sent. It takes four weeks.

Alex: We don't have that folder.

The variation

Alex's firm charges for the rework. Fair enough: nobody asked them for it before they priced. Kofi, the commercial manager, gets the bill.

The client told us what it needed. We kept it in a folder, and paid Alex to find out.

+4 weeks on the back alley's bill: The order never passed on: every firm drew in its own style, and four weeks of renaming and rework, paid for twice.