Stage 3 · Get ready · Stop 6 of 8 · The right way

Who makes what, and when

The back alley's bill so far: 61 weeks · See the bill

← Back to the wrong way

The right way

Get readyGet ready: Month one…
The parts list

Every drawing, model and record on it, with a firm, a person and a date. The inlet chamber drawing is due in week 6.

Linked to the programme

Owen links the parts list to the build programme. When the programme moves, the drawing dates move with it.

DesignDesign: Month two…
On time

The inlet chamber drawing arrives in week 6, as listed. The fence, which isn't on the list, gets a modest drawing, which is all a fence needs.

Last opened at tenderA gorgeous fence and a missing chamber.
Kept aliveEvery drawing with a name and a date, moving with the programme.

Now there is: The whole parts list (the master information delivery plan), with every firm's parts, linked to the programme and kept live.

What's going on here

The parts list is how a job knows what it's making, who's making it and when. Linked to the programme and kept live, it means the drawing site needs next week is already on someone's desk, and a drawing nobody asked for is a sign it's being ignored.

In the town See it in the town: Who's making the drawing site needs next week?

The parts list started life in each deal with the neighbours, one firm's lines at a time. Here it becomes the whole job's parts list, every firm's lines in one place, on the published shelf beside the promise and tied to the build programme so the dates move together. Kept live, it shows a missing inlet chamber drawing early, and a lovingly detailed fence nobody ordered just as quickly.

Fix it Parts list gathering dust? Bring it back to life.
  1. Check the next month's site activities against the parts list.
  2. Add anything missing with a firm, a person and a date.
  3. Link the list to the programme and review both together weekly.

A note for the information manager: Watch for drawings nobody listed as closely as listed ones running late, because both mean the list has stopped steering the work.

Try it on your job

Find the next drawing your site needs. Is it on the parts list, with a name and a date?

From the standard
ISO 19650 From each firm's list to the whole job's
ISO 19650 saysMeansIn the town
Master information delivery plan (MIDP)the single plan of all the information the job will deliver, gathered from every task team, with who and whenthe whole parts list
Task information delivery plan (TIDP)each task team's own schedule of what it will produce and by wheneach firm's lines on the parts list
Information delivery milestonea set point in the job by which particular information must be deliveredthe date against each line, moving with the programme

Based on the ISO 19650 series: the ideas come from the standard; the plain-English wording, examples and advice are InfoTown's. ISO 19650 and its UK National Annex are © ISO and BSI. You'll hear the same language across the industry. Read more for free in the Information Management Initiative (IMI) Framework guidance from BSI and nima. For the full requirements, use the standard itself.