The lessons-learned meeting turns into who blames whom. Nothing gets written down.
It's all on the drive
The back alley's bill so far: 154 weeks · See the bill
The team's moving on. Somebody has to close the door behind them, and decide how long to keep me.
The wrong way
Callum, the project manager, and Dave, the site manager, plan the move.
Callum: Where's it all going?
Dave: The drive.
Callum: Which drive?
Dave: The drive.
Nobody closes the job. Every firm can still log in, including the fencing firm, one of whose people now works for a competitor.
Finance spots the bill for 300 jobs nobody closed. IT tidies the drive and deletes everything older than a year. Including The Glasshouse.
Grace, the client's asset manager, raises a defect on the inlet chamber and asks Kofi, the commercial manager, for the inspection records.
Kofi: They're on the drive.
Grace: Which drive?
Nobody can show the inspection was done, so the firm pays for the repair. Kofi books it to the rework cost code. Nobody's counting that either.
Kept safe on the drive, until somebody tidied the drive. The defect claim arrived after.
+3 weeks on the back alley's bill: Nobody closed the doors: the records deleted, a defect nobody could defend, and the leavers still logged in.