Stage 2 · Win the work · Stop 11 of 11

Signed, sealed

The back alley's bill so far: 42 weeks · See the bill

The information · The contract

They've won. The promise goes into the contract now. I'm a promise with a signature on it.

The wrong way

Win the workWin the work: Award…
We won

The client picks the firm. There's cake. Everyone goes to the cake.

The signature

Helen, the divisional director, signs the contract. The information requirements are in Appendix K. Nobody opens Appendix K.

The subcontracts

The subcontracts go out without the client's order in them. The subbies sign up to drawings "by others".

DesignDesign: Month four…
The client asks

The client asks why the asset data isn't being collected. Nobody on the job has been asked to collect it.

Appendix K

Helen and Sam, the firm's information manager, open Appendix K at last.

Helen: What did we sign?

Sam: Appendix K.

Helen: What's in Appendix K?

Sam: Everything.

Re-papering

Two weeks re-papering every subcontract, this time with the order inside. Bev, who buys everything the job needs, runs out of staples.

The cake was eaten in ten minutes. Appendix K took the rest of the job.

+2 weeks on the back alley's bill: Nobody read what was signed, and the subbies never got the order: two weeks re-papering every subcontract.