The plan for day one

The back alley's bill so far: 37 weeks · See the bill

The information · The plan for day one

If they win, I'll need somewhere to live on the first morning. Plan it now, while it's still cheap.

The wrong way

Win the workWin the work: Tender · week four…
Everyone agrees

Everyone agrees day one matters, including Tom, the bid manager. Nobody writes anything down.

Tom: We'll sort mobilisation when we mobilise.

The blank sheet

The bid goes in. The sheet on the wall marked DAY ONE stays blank, apart from a small drawing of a sun.

The password

The firm wins. Someone sets up one login for the Site Office and writes the password on a sticky note. It goes on site manager Dave's van.

Get readyGet ready: Day one…
The queue

Forty people arrive at a Site Office with no logins.

Leeds

The only working password is on Dave's van. Dave is in Leeds.

Week six

By week six, everyone is saving drawings wherever they can. Callum, the project manager, finds one in the microwave.

Callum: I said I wasn't finding out in week six.

Everyone agreed day one mattered. Nobody planned it. Dave was in Leeds.

+2 weeks on the back alley's bill: No plan for day one: no logins, drawings everywhere, and two weeks getting them back in one place.