Stage 2 · Win the work · Stop 4 of 11 · The right way

Who's actually doing this?

The back alley's bill so far: 24 weeks · See the bill

← Back to the wrong way

The right way

Win the workWin the work: Tender · week two…
Names and hours

Sam, the firm's information manager, fills the empty box: who manages the information, who controls the documents, who checks, and how much of their week it takes.

Sam: Two and a half people. Not 'the IM team'.

The same pack

Bev sends every subcontractor the same pack, with the same order inside. Three quotes come back, all pricing the same information. For once, Bev can compare them.

Bev: Apples with apples. I could cry.

DesignDesign: Month two of the job…
Nobody's surprised

The named people are on site, with the hours. The electricians deliver what they priced.

The IM teamNobody's name, three packs, and "by others".
Names and hoursTwo and a half people, one pack, three comparable quotes.

Now there is: The people who'll look after the information, named, with hours against them (the information management function). The same pack for every subcontractor (the tender response requirements).

What's going on here

Information doesn't look after itself, and "the team" isn't a person. Naming who does it, and the hours it takes, is part of the price. Sending every subcontractor the same pack is what makes their quotes comparable.

In the town See it in the town: who looks after all of this?

The order in the bid room asks for a lot of information, and somebody has to look after it on the job: not a box on an org chart, but named people with hours. The same order then travels out from the bid room to every subcontractor in an identical pack, so their quotes price the same thing. Send different packs, and the order arrives in three versions, or not at all.

Fix it Nobody's name in the box? Put one there this week.
  1. Write a name, and hours a week, against each information task.
  2. Check the hours fit alongside everything else that person is doing.
  3. Resend every subcontractor the same pack, with the order inside.

A note for the information manager: "The IM team" isn't a resource until it has names and hours, and "by others" usually means you.

Try it on your job

Look at your job's org chart. Is there a name, with hours, against looking after the information?

From the standard
ISO 19650 From an empty box to names and hours
ISO 19650 saysMeansIn the town
Information management functionThe roles and people responsible for managing information on the job, whoever employs themThe names in the box: Sam's two and a half people
Tender response requirementsWhat each bidding firm must send back to show how it will meet the information requirementsThe same pack sent to all three electricians
Task teamA group of people doing one part of the work, such as a subcontractorThe electricians, each pricing the same order

Based on the ISO 19650 series: the ideas come from the standard; the plain-English wording, examples and advice are InfoTown's. ISO 19650 and its UK National Annex are © ISO and BSI. You'll hear the same language across the industry. Read more for free in the Information Management Initiative (IMI) Framework guidance from BSI and nima. For the full requirements, use the standard itself.