Stage 5 · Build it · Stop 3 of 13

Hold points

The back alley's bill so far: 101 weeks · See the bill

The information · An inspection, before the pour

Some of me has to exist before the concrete does. An inspection record can't be written after the pour.

The wrong way

BuildBuild: Thursday…
The base slab

The basement's base slab. The steel is fixed on Thursday. The concrete is booked for Friday at 7am, because concrete is always booked for Friday at 7am.

Page 30

The client's plan says the Clerk of Works, the client's eyes on site, inspects the steel before any pour. It's on page 30. Nobody on site has met page 30.

BuildBuild: Friday, 6.55am…
Six trucks

Six trucks queue at the gate. Priya, who looks after quality and safety, rings Dave, the site manager.

Priya: Has the steel been inspected?

Dave: It looked fine. Pour it.

BuildBuild: Monday…
Show me

The Clerk of Works asks for the inspection record. There isn't one. There are four photos on Dave's phone, three of them of his thumb.

The cores

Cores are drilled through the brand-new slab to prove the steel is there. Three neat cylinders, lined up like trophies.

Three weeks

The steel was there. It took three weeks to find out.

Priya: If it isn't written down, it didn't happen.

Clerk: Exactly.

The steel was probably fine. Probably took three weeks and a core drill to prove.

+3 weeks on the back alley's bill: A pour with no inspection record: cores through a new slab, and three weeks proving what nobody wrote down.

See the right way