The monthly report

The back alley's bill so far: 122 weeks · See the bill

The information · The monthly report

The board reads a number made from me. Every number should say where it came from, who owns it, and how fresh it is.

The wrong way

BuildBuild: Quarterly review…
The dashboard

Callum, the project manager, builds the monthly dashboard from four spreadsheets that disagree. It's beautiful. The Glasshouse is on budget: a lovely green bar.

The board

Helen, the divisional director, tells the board. The board is pleased. Nobody asks where the green came from.

Behind the bar

The green comes from a spreadsheet on someone's desktop, last updated before the basement went two metres deeper. The real number is in an email nobody forwarded.

BuildBuild: Two weeks later…
Overnight

The bar turns red overnight. It was a feeling, not a forecast.

The call

Helen's phone rings. She holds it at arm's length.

Gordon (chief executive): The board would like a word.

The rebuild

Callum spends a fortnight rebuilding the forecast. The four spreadsheets still disagree, but now everyone knows they do.

The green bar was a feeling. The red one came with a phone call.

+2 weeks on the back alley's bill: A dashboard built from spreadsheets nobody owned: a forecast that was wrong for two months, and a fortnight rebuilding it.