Stage 5 · Build it · Stop 5 of 13

Site records

The back alley's bill so far: 110 weeks · See the bill

The information · Diaries, inspections and readings

Every day on site makes more of me: diaries, inspections, readings, fixes. If I'm not written down, I didn't happen.

The wrong way

BuildBuild: All year…
The red binder

Every signed inspection sheet goes into a red ring binder in the site cabin. Forty of them. Very tidy. Bottom shelf, next to the kettle.

DesignDesign: Month five…
The readings

Every morning Stevie, the site engineer, reads the targets on the basement dig, three metres from the old Precinct. One reading turns amber. The PDF goes to 23 people.

Fixed by lunch

A precast chamber arrives with the pipe opening on the wrong side. Site drills a new hole, grouts the old one. Nobody tells the designer. "Sorted."

BuildBuild: November…
The river

The river next door has opinions. The cabin floods to the knee. The red binder is soup.

The crack

Eight days after the amber cell, the old Precinct's wall cracks. The warning is still somewhere in 23 inboxes.

Three weeks

Two drainage runs re-tested, the patched chamber cored, the dig stopped beside the old Precinct. The Clerk of Works, the client's eyes on site, has a question.

Clerk: When did you know?

Stevie: Tuesday. Last week.

Forty records in one binder, one amber cell in 23 inboxes, one patch nobody mentioned, and a river with opinions.

+3 weeks on the back alley's bill: Records kept where floods and inboxes could eat them: re-tests, cores, and the dig stopped beside a cracked old Precinct.

See the right way