The information · A licence, a notice, and a cable nobody drew

The ground knows things the drawings don't. When it tells you, write it down the same day, and tell the people who need to know.

The wrong way

BuildBuild: At design stage…
Appendix F

The ecologist finds protected newts in the pond. The licence conditions go into Appendix F of the environmental report. The site drawings show a pond. Just a pond.

BuildBuild: March…
The digger

No fence, no ecologist. The digger strips to the pond. Rex, the new assistant engineer, finds a newt in the bucket. Then he sees quality and safety manager Priya's face.

Sand and a cable

The digger hits wet sand, not the survey's clay, then an old cable on no drawing. The gang nudges it aside. The minutes say "ground conditions discussed".

BuildBuild: Week nine…
The notice

The contract says: tell the client, in writing, to the named person, within eight weeks. Someone emails the notice to a client manager from the tender. She left in March.

Six weeks

The newts stop the job until the next licence window. Kofi, the commercial manager, watches the ground claim fail: late, and to the wrong person.

Kofi: Eight weeks. It was in bold.

The secret

And the cable? Still in the ground, on no drawing. One day somebody will dig there again, and it'll be a surprise all over again.

The newts were in the report, the notice went to someone who'd left, and the cable is still a secret.

+6 weeks on the back alley's bill: The rules nobody saw, a late notice to the wrong person, and a cable nobody wrote down: six weeks waiting and a claim that failed.