Late, not extra

The back alley's bill so far: 117 weeks · See the bill

The information · A drawing, three weeks late

I was due three weeks ago. When I arrive late, that's a delay, and the dates on me prove it, if anyone kept them.

The wrong way

BuildBuild: Month seven…
Three weeks late

The designer is late with the valve chamber drawing. Site waits three weeks for it, with a gang standing by.

How it arrived

It comes by email. To Dave, the site manager. Then forwarded to a site engineer. Then a revised one to someone on holiday.

The search

Kofi, the commercial manager, needs to prove when it arrived. Six people search their inboxes. Six different answers, two emptied folders.

BuildBuild: The claim…
Two dates

The client's records say the drawing was issued on the 3rd. Ours show a forwarded email from the 24th, with no attachment.

Not one day

Kofi lays out everything he's got. It isn't much.

Kofi: Three weeks standing time, and I can't prove one day.

Failed

The claim fails. The firm pays for three weeks of a gang sitting on buckets. The buckets, at least, were free.

Three weeks late, six inboxes, and not one day anyone could prove.

+3 weeks on the back alley's bill: A delay nobody could prove: three weeks of a waiting gang, paid for by the firm.