Stage 5 · Build it · Stop 1 of 13 · The right way

Ordered off the current revision

The back alley's bill so far: 95 weeks · See the bill

← Back to the wrong way

The right way

BuildBuild: Week six…
The check

Before ordering, Bev opens the specification on the published shelf in the Site Office. It changed a fortnight ago: C02. The order quotes C02.

Keys on day one

Nicole's gang gets its logins and a half-hour tour of the Site Office on day one. Nicole checks her prints against the published shelf. Two are old. She bins them.

Nicole: Recycling. Very green.

BuildBuild: Week twenty…
The delivery

The escalators arrive. Stevie checks the nameplates against the schedule. They match. They fit the bases.

The inbox copyThe wrong escalators, sixteen more weeks, and pits cast for the old size.
The published shelfThe right escalators, the right pits, and a very green bin.

Now there is: Orders and subcontract work from the published shelf (published information, current version).

What's going on here

An order is information leaving the job, so it carries the version it was placed against. Ordering from the published shelf, and giving every new firm its keys and a tour on day one, means everyone buys and builds from the same current version, not whatever was in their inbox or their office printer.

New at this stop

Keys on day one
Logins and access for a new firm, set up the day it starts.
In the town See it in the town: An inbox copy looks just as official. Does it know it's old?

The escalator order is information leaving the job for a supplier, so it carries a revision with it. C02 had been on the published shelf in the Site Office for a fortnight, while C01 sat in Bev's inbox looking smart. New firms bring old copies too, like Nicole's March prints. Keys on day one give every new gang a way into the Site Office, so the shelf, not the inbox or the office printer, is where everyone buys and builds from.

Fix it Orders already out? Check which revision they quote.
  1. List this month's orders and the revision each was placed against.
  2. Compare each with the current revision on the published shelf.
  3. Give any firm still without logins its keys this week.

A note for the information manager: Make the revision number a required field on every order form, so "which spec?" gets answered before the lorry arrives.

Try it on your job

Pick one order placed on your job this month. Does it say which version of the specification it was placed against?

From the standard
ISO 19650 From the shelf to the order
ISO 19650 saysMeansIn the town
Published stateInformation authorised and accepted for use, with the current revision clearThe published shelf, where C02 lives
MobilisationGetting a team ready before it starts: access to the shared environment set up and tested, and people trained to use itKeys on day one
Not from ISO 19650: the purchase orderA commercial document sent to a supplier. It should name the revision of the specification it was placed againstBev's order, carrying C02 out of the Site Office

Based on the ISO 19650 series: the ideas come from the standard; the plain-English wording, examples and advice are InfoTown's. ISO 19650 and its UK National Annex are © ISO and BSI. You'll hear the same language across the industry. Read more for free in the Information Management Initiative (IMI) Framework guidance from BSI and nima. For the full requirements, use the standard itself.